Central Reclamation,
Phase III
Quarterly EM&A
Report No. 13
(August 2006 through
October 2006)
|
Client |
Civil Engineering Development Department, |
|||||||
|
Project |
Supplementary Agreement No. 3 to Agreement No. CE
15/94 Design and Construction for the Minimum Option |
|||||||
|
Report
No. |
3128-REP-256-00 |
|||||||
|
Date of Issue |
14 November 2006 |
File
Ref. L:\S-proj\CR3\CR3.NEW\3128\ |
||||||
|
Report Title |
Central Reclamation, Phase III Quarterly EM&A Report No. 13 August 2006 through October 2006 |
|||||||
|
|
Name |
|
Sign |
|
Date |
|
||
|
Prepared
by : |
Roger
Leung, ACL – Principal Consultant |
|
|
|
14
November 2006 |
|
||
|
Reviewed by: |
Susana
Bezy, ACL – ET Leader |
|
|
|
14
November 2006 |
|
||
|
Authorised by : |
Jon
Varndell, ACL – Project Mgr |
|
|
|
14
November 2006 |
|
||
|
|
|
|
||||||
|
Distribution |
|
|
||||||
|
Copy No |
Issue to |
Attention |
Corr. Ref. |
|||||
|
1 |
CEDD |
Mr.
Eric K.W. Fung |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
2, 3 |
EPD |
Director
of EPD |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
4 |
EPD
(Environmental Compliance Div.) |
Mr.
Samson Cheng |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
5 |
Leighton-China
State-Van Oord JV |
Mr.
Malcolm Plummer |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
6 |
CRIII Sites/PRE |
Mr.
Douglas Miller |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
7 |
Independent
Checker (Environment) |
Mr.
Bill Douglas |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
8 |
Environmental
Team Leader |
Ms
Susana Bezy |
3128/M45/200/OC8753/SB/DRS/ec |
|||||
|
9 |
Office
Copy |
|
|
|||||
|
|
|
|
|
|||||
|
|
|
|
|
|||||
|
|
|
|
|
|||||
|
|
|
|
|
|||||
|
|
|
|
|
|||||
1.2 Project Organisation and
Management Structure
2.1 Summary of Impact EM&A Requirements
2.2 Environmental Quality Performance Limits
3.1 Implementation of Environmental Measures
3.2 Environmental Monitoring Locations
3.3 Air Quality Monitoring Results
3.4 Noise Quality Monitoring Results
3.5 Water Quality Monitoring Results
3.6 Solid and Liquid Waste Management Status
3.7 Landscape and Visual Audit
4. Environmental Complaint and Non-Compliance
4.3 Summary of Actions Taken by the Contractor
4.5 Environmental Complaints and Prosecutions
4.6 Record of Environmental Complaints and Summons
& Prosecutions
List of Annexes
Annex A Project Organisation/ Contact Information
Annex B Quality Performance Limits for Air, Noise and Water Quality
Annex C Event and Action Plans for Air, Noise and Water Quality
Annex D Monitoring Stations Locations
Annex E Contractor's Works Programme
Annex F Graphical Representation of Air Quality Monitoring Results
Annex G Graphical Representation of Noise Quality Monitoring Results
Annex H Graphical Representation of Water Quality Monitoring Results
Annex I Quarterly Assessment of Construction Impacts on Suspended Solids
List of Tables
Table
2.1 - Summary of Impact EM&A Requirements....................................................................... 3
|
ACL |
Atkins China Limited |
|
CEDD |
Civil Engineering and Development Department |
|
CRIII |
Central Reclamation Phase III |
|
EIA |
Environmental Impact Assessment |
|
EM&A |
Environmental Monitoring and Audit |
|
EPD |
Environmental Protection Department |
|
ER |
Engineer’s Representatives |
|
ET |
Environmental Team |
|
IEC |
Independent Environmental Checker |
|
LCSD |
Leisure and Cultural Services Department |
|
LCSVO-JV |
Leighton-China State-Van Oord Joint Venture |
|
TDD |
Territory Development Department |
|
TSP |
Total Suspended Particulates |
Executive Summary
The Central Reclamation Phase III (CRIII) Works, Contract No. HK 12/02,
was awarded to Leighton China State Van Oord Joint Venture (LCSVO-JV) by the
Civil Engineering and Development Department (CEDD). (Previously called the
Territory Development Department before merger with the Civil Engineering
Department on 1 July 2004.)
The works under the Contract HK 12/02 commenced on 28 February
2003. Contract HK 16/03 for the CRIII
Hinterland Drainage Improvement Works was awarded to Wang Kee Construction Co.
Ltd., and works for this contract commenced on 17 December 2003.
Atkins China
Limited (ACL) has been commissioned by
CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring
and Audit (EM&A) programme described in the approved EM&A Manual for
the CRIII Project.
This is the 12th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from 1
August 2006 to 31 October 2006.
Environmental Monitoring and Audit Progress
Air, Noise and
water quality monitoring were conducted during this quarter. Weekly environmental site inspections were also
conducted during the reporting quarter.
Exceedance of Action and Limit Levels
From August to October 2006, no exceedance of the AL or LL for TSP was
recorded.
Noise exceedances were recorded on the 10 August and 19 August 2006 at
the City Hall monitoring station. There have been periods of failure and calibration of the meter near
the end of September and beginning of October.
Water quality exceedances for this quarter are tabulated below:-
|
04-Aug-06 |
Mid-Ebb |
DO |
AL |
M4A |
|
Mid-Flood |
DO |
AL |
M3, M4A, M5, M6, M11 and M12 |
|
|
07-Aug-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M5, M6, M8 (S/M),
M11 and M12 |
|
|
09-Aug-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
|
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11,
M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
Mid-Flood |
SS |
AL |
M11 |
|
|
14-Aug-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M10 (S/M), M11 and M12 |
|
|
Mid-Flood |
SS |
AL |
M12 |
|
|
16-Aug-20 |
Mid-Ebb |
DO |
AL |
M5 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
21-Aug-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M5, M6, M11 and M12 |
|
LL |
M4A |
|||
|
Mid-Flood |
DO |
AL |
M2A, M3, M5, M6 and M12 |
|
|
LL |
M4A |
|||
|
Mid-Flood |
SS |
AL |
M4A |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M8 (B), M10 (S/M), M11, M12 |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M8 (B), M10 (S/M), M10 (B), M11 and M12 |
|
|
Mid-Flood |
SS |
LL |
M4A |
|
|
|
Mid-Ebb |
DO |
|
M2A, M3, M4A and M5 |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and M12 |
|
|
|
Mid-Ebb |
DO |
|
M3 and M4A |
|
Mid-Flood |
DO |
|
M3, M4A, M6, M8 (S/M) and M10
(S/M) |
|
|
|
Mid-Ebb |
DO |
|
M3 and M4A |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M6, M11 and M12 |
|
|
|
Mid-Ebb |
DO |
|
M4A and M8 (B) |
|
Mid-Flood |
DO |
|
M4A, M8 (B) and M10 (B) |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A and M10 (S/M) |
|
LL |
M8 (S/M), M8 (B) and M10 (B) |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M8 (B), M10 (S/M), M10 (B) and M12 |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M5, M6, M11 and M12 |
|
LL |
M4A |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M8 (B),
M10 (B) and M11 |
|
LL |
M8 (S/M) and M10 (S/M) |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M6, M8 (B), M10
(B), M11 and M12 |
|
|
LL |
M8 (S/M) and M10 (S/M) |
|||
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
LL |
M8 (S/M) and M10 (S/M) |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
LL |
M8 (S/M) and M10 (S/M) |
|||
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M8
(S/M), M10 (S/M), M11 and M12 |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M10
(S/M), M11 and M12 |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M5, M6, M8 (S/M),
M10 (S/M), M11 and M12 |
|
LL |
M4A |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M6, M8 (S/M),
M10 (S/M), M11 and M12 |
|
|
LL |
M5 |
|||
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M5, M6, M8 (S/M),
M11 and M12 |
|
LL |
M4A |
|||
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M10
(S/M), M11 and M12 |
|
|
LL |
M8 (S/M) |
|||
|
|
Mid-Flood |
SS |
|
M1A, M8, M10 and M11 |
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
|
SS |
|
M1A |
||
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and M12 |
|
Mid-Flood |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M11 and M12 |
|
|
|
Mid-Flood |
SS |
|
M3 |
|
LL |
M4A |
|||
|
|
Mid-Ebb |
DO |
|
M2A, M3, M4A and M5 |
|
Mid-Flood |
DO |
|
M2A, M3, M4A and M11 |
|
|
|
Mid-Ebb |
DO |
|
M1A, M2A, M3, M4A, M5, M6, M10(S/M), M11 and M12 |
|
SS |
|
M4A |
||
|
Mid-Flood |
DO |
|
M8(S/M), M10(S/M) and M12 |
|
|
SS |
|
M6 |
||
|
LL |
M12 |
|||
|
|
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M10(S/M), M11
and M12 |
|
|
9-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M10(S/M), M10(B), M11
and M12 |
|
|
SS |
AL |
M5, M10 and M12 |
||
|
LL |
M6 |
|||
|
11-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(B), M10(S/M),
M10(B), M11 and M12 |
|
LL |
M8(S/M) |
|||
|
Mid-Flood |
DO |
AL |
station M1A, M2A, M3, M4A, M5, M6, M8(S/M),
M8(B), M11 and M12 |
|
|
SS |
AL |
M5 |
||
|
LL |
M3 |
|||
|
13-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
SS |
AL |
M4A |
||
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
|
SS |
AL |
M5 |
||
|
LL |
M4A |
|||
|
16-Sep-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(B), M10(S/M),
M10(B), M11 and M12 |
|
|
SS |
AL |
M4A and M5 |
||
|
18-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
|
SS |
LL |
M6 and M12 |
||
|
20-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
|
SS |
AL |
M12 |
||
|
23-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
|
SS |
AL |
M4A and M11 |
||
|
LL |
M1A |
|||
|
25-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M3, M4A, M5, M6, M8(S/M), M8(B), M10(S/M),
M10(B), M11 and M12 |
|
SS |
AL |
M1A |
||
|
LL |
M4A |
|||
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(B), M11 and M12 |
|
|
SS |
AL |
M6 |
||
|
LL |
M12 |
|||
|
27-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and M12 |
|
SS |
AL |
M1A, M4A, M5 and M11 |
||
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
|
SS |
AL |
M1A, M6 and M12 |
||
|
28-Oct-06 |
Mid-Flood |
SS |
AL |
M4 |
|
31-Oct-06 |
Mid-Ebb |
DO |
AL |
M1A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
|
Mid-Flood |
DO |
AL |
M1A, M3, M4A, M5, M6, M8(S/M), M8(B),
M10(S/M), M10(B), M11 and M12 |
Complaint Log
There were no complaints received in relation to environment impact
during the reporting period.
Notifications
of Summons and Prosecutions
There were
no notifications of summons or prosecutions received during this reporting
quarter.
Site Inspection and Audit
Weekly environmental site inspections were
carried out during this quarter. Minor deficiencies
noted during the site inspections were rectified by the Contractor upon receipt
of notification.
The Main Works Contract HK 12/02 for CRIII commenced on 28th February
2003 and was awarded to Leighton-China State-Van Oord Joint Venture (LCSVO-JV)
for the construction of the CRIII Engineering Works. The main construction works that were
identified in the EIA Report for the Project, requiring environmental
monitoring and audit, have commenced.
This is the 12th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from 1
August 2006 to 31 October 2006.
The
Contractor's works programme for the quarter is provided in Annex
E.
Atkins China
Limited (ACL) has been commissioned by
CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring
and Audit (EM&A) programme described in the approved EM&A Manual and
required under Clause 4 of the Further Environmental
Permit (No. FEP-01/122/2003) issued to Leighton-China State-Van Oord Joint
Venture in May 2005 for the CRIII Project. An Independent Environmental Checker (IEC) has been employed to audit
the EM&A programme.
The CRIII Project Organisation is shown in Annex A.
The works undertaken in the project area requiring environmental
monitoring and audit as identified in the EIA Report during the quarter
included:
·
Fitting out works by the ferry operators at Piers 7
& 8 and at the CTB;
·
Remedial and outstanding works and additional
modification works at Piers 7 & 8;
·
Remedial and outstanding works and additional
modification works at the CTB;
·
Deck and roof column construction works and
structural steel works for the roof and finishing works at Public Pier
West;
·
Finishing works and landscaping works at and
adjacent to the new ferry piers;
·
Testing and Commissioning and the trial runs of
Pump Stations P9.1 and P11.1;
·
MYS Footbridge –main span erection and in-situ deck
construction;
·
General filing works above +2.5mpd in IRAE;
·
Construction of storm and foul drainage in IRAE;
·
Structural works for Culvert J extension in IRAE;
·
Excavation for PLA cooling water intake in IRAE;
·
Temporary works for Road P2 Underpass;
·
Bored piling at Eastern Seawall and;
·
Cooling water main construction in
The EM&A
programme requires environmental monitoring for air quality, noise, water
quality, waste management and landscape and visual aspects as specified in the
CRIII Project EIA. The EM&A
requirements for each issue area are described in subsequent sections
including:
·
All required monitoring parameters;
·
Action and Limit Levels; and
·
Event-Action Plans.
A summary of
impact EM&A requirements is presented in Table 2-1.
|
Parameters |
Descriptions |
Locations |
Frequencies |
Duration |
||
|
TSP |
24-Hour
TSP |
2
Locations |
Once
every 6 days |
During
dust generating construction works |
||
|
1-Hour
TSP |
2
Locations |
Three
times in every 6 days |
During
dust generating construction works |
|||
|
Noise |
Leq (30 mins), L10, L90, |
1
Location |
Continuous
measurements |
Two
weeks before Construction and During Construction |
||
|
Water
Quality |
Dissolved
Oxygen; Salinity; Temp; Suspended
Solids; Turbidity. |
14
Locations |
3 times
a week, Mid-ebb/flood tides |
During
Marine Works and for 4 weeks after completion of Marine Works |
||
|
Waste |
On-Site
Waste Audit |
Active
Work Sites |
Periodically |
During
Construction |
||
|
On-Site
Waste Inspection |
||||||
|
Landscape
and Visual |
Audits
to ensure effective implementation of mitigation measures |
During Construction |
||||
|
General
Site Conditions |
Environmental
Site Inspection |
Works
areas and areas affected by works |
Periodically |
During
Construction |
||
Environmental
Quality Performance Limits for air, noise and water quality have been
established as part of the Baseline Monitoring Report and are provided in Annex
B.
Event Action
Plans for air, noise and water quality have been developed as part of the
Baseline Monitoring Report and are provided in Annex C.
The Contractor has
implemented relevant mitigation measures listed in the EIA Report, EM&A
Manual and Further Environmental Permit.
Drawings showing
the project area and locations of the monitoring stations are provided in Annex
D.
The graphical
plot of air quality monitoring results is provided in Annex F.
The graphical
plot of noise monitoring results for this quarter is provided in Annex G.
The graphical
plot of water quality monitoring results for this quarter is provided in Annex
H.
Solid and liquid
waste management was implemented according to the Waste Management Plan during
the reporting quarter.
As the works undertaken during the reporting quarter were mainly related
to reclamation, buildings and infrastructure works, the landscape and visual
impacts are considered to be minimal.
No exceedances of the AL or LL for TSP were recorded during August 2006
and October 2006.
Two noise exceedances were recorded on the 10 August and 19 August 2006
at the City Hall monitoring station. There was no
construction activity on- site on the 10 Aug06. About 6,000 lighting strokes were
recorded in Hong Kong
during the monitoring period on 19-Aug-06. Therefore, the noise exceedances were not attributable to project works.
Water quality exceedances of DO and SS recorded during August, September
and October 2006 are detailed below.
|
04-Aug-06 |
Mid-Ebb |
DO |
AL |
M4A |
|
Mid-Flood |
DO |
AL |
M3, M4A, M5, M6, M11 and M12 |
|
|
07-Aug-06 |
Mid-Ebb |
DO |
AL |
M1A, M2A, M3, M4A, M5, M6, M11 and
M12 |
|
Mid-Flood |
DO |
AL |
M1A, M2A, M3, M5, M6, M8 (S/M),
M11 and M12 |
|
|
09-Aug-06 |
Mid-Ebb |
DO |
AL |