Central
Reclamation, Phase III
Quarterly
EM&A Report No. 18
(November
2007 through January 2008)
|
Client |
Civil Engineering Development Department, |
||||||
|
Project |
Supplementary Agreement No. 3 to Agreement No. CE 15/94 Design and Construction for the Minimum Option |
||||||
|
Report
No. |
3128-REP-299-00 |
||||||
|
Date of Issue |
|
File
Ref. L:\S-proj\CR3\CR3.NEW\3128\ |
|||||
|
Report Title |
Central Reclamation,
Phase III Quarterly EM&A
Report No. 18 November 2007 through
January 2008 |
||||||
|
|
Name |
|
Sign |
|
Date |
|
|
|
Prepared by: |
Wing
Wong, ACL - |
|
|
|
|
|
|
|
Reviewed by: |
Susana
Bezy, ACL – ET Leader |
|
|
|
|
|
|
|
Authorised by:
|
Jon
Varndell, ACL – Project Mgr |
|
|
|
|
|
|
|
|
|
|
|||||
|
Distribution |
|
|
|||||
|
Copy No |
Issue to |
Attention |
Corr. Ref. |
||||
|
1 |
CEDD |
Mr.
Eric K.W. Fung |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
2,
3 |
EPD |
Director
of EPD |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
4 |
EPD
(LCO) |
Miss
W. Y. Yiu |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
5 |
Leighton-China
State-Van Oord JV |
Mr.
Malcolm Plummer |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
6 |
CRIII Sites/PRE |
Mr.
Douglas Miller |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
7 |
Independent
Checker (Environment) |
Mr.
Bill Douglas |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
8 |
Environmental
Team Leader |
Ms
Susana Bezy |
3128/M45/200/OC10078/SB/DS/KC/ec |
||||
|
9 |
Office
Copy |
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
|
|
|
|
|
||||
1.2 Project Organisation and Management Structure
2.1 Summary of Impact
EM&A Requirements
2.2 Environmental Quality
Performance Limits
3.1 Implementation of
Environmental Measures
3.2 Environmental
Monitoring Locations
3.3 Air Quality Monitoring
Results
3.4 Noise Quality
Monitoring Results
3.5 Water Quality
Monitoring Results
3.6 Solid and Liquid Waste
Management Status
3.7 Landscape and Visual
Audit
4. Environmental Complaint and Non-Compliance
4.3 Summary of Actions
Taken by the Contractor
4.5 Environmental
Complaints and Prosecutions
4.6 Record of
Environmental Complaints and Summons & Prosecutions
List of Annexes
Annex A Project Organisation/ Contact Information
Annex B Quality Performance Limits for Air, Noise and Water Quality
Annex C Event and Action Plans for Air, Noise and Water Quality
Annex D Monitoring Stations Locations
Annex E Contractor's Works Programme
Annex F Graphical Representation of Air Quality Monitoring Results
Annex G Graphical Representation of Noise Quality Monitoring Results
Annex H Graphical Representation of Water Quality Monitoring Results
Annex I Quarterly Assessment of Construction Impacts on Suspended Solids
List of Tables
Table 2.1 - Summary of Impact EM&A
Requirements
|
ACL |
Atkins China Limited |
|
|
Action Level |
|
CEDD |
Civil Engineering and Development Department |
|
CRIII |
Central Reclamation Phase III |
|
DO |
Dissolved Oxygen |
|
EIA |
Environmental Impact Assessment |
|
EIAO |
Environmental Impact Assessment Ordinance |
|
EM&A |
Environmental Monitoring and Audit |
|
EPD |
Environmental Protection Department |
|
ER |
Engineer’s Representatives |
|
ET |
Environmental Team |
|
IEC |
Independent Environmental Checker |
|
LCSD |
Leisure and Cultural Services
Department |
|
LCSVO-JV |
|
|
LL |
Limit Level |
|
PLA |
People's Liberation Army Forces |
|
TDD |
Territory Development Department |
|
TSP |
Total Suspended Particulates |
|
SS |
Suspended Solids |
|
WMP |
Waste Management Plan |
Executive Summary
The Central Reclamation Phase III (CRIII) Works, Contract No. HK 12/02, was
awarded to Leighton China State Van Oord Joint Venture (LCSVO-JV) by the Civil
Engineering and Development Department (CEDD). (Previously called the Territory
Development Department before merger with the Civil Engineering Department on
The works under the Contract HK 12/02 commenced on
Atkins China
Limited (ACL) has been commissioned by
CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring
and Audit (EM&A) programme described in the approved EM&A Manual for
the CRIII Project.
This is the 18th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from
Environmental Monitoring and Audit Progress
Air quality,
noise and water quality monitoring were conducted during this quarter. Weekly environmental site inspections were
also conducted during this reporting quarter.
Exceedance of Action and Limit Levels
No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.
One noise exceedance was recorded at the City Hall
monitoring station in this reporting quarter. The exceedance has been investigated and was considered to
have been attributed to other external factors and unlikely to be related to
project works.
Water quality exceedances were recorded on 15 sampling days in this
reporting quarter. The exceedances have
been investigated and were considered to be attributed to other external
factors and unlikely to be related to project works.
Complaint Log
There were no complaints received in relation to environment impact
during this reporting quarter.
Notifications
of Summons and Prosecutions
There were
no notifications of summons or prosecutions received during this reporting
quarter.
Site Inspection and Audit
Weekly environmental site inspections were carried out during this
quarter. Minor deficiencies noted during
the site inspections were rectified by the Contractor upon receipt of
notification.
The Main Works Contract HK 12/02 for CRIII commenced on
This is the 18th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from
The
Contractor's works programme for the quarter is provided in Annex
E.
1.2
Project
Organisation and Management Structure
Atkins China
Limited (ACL) has been commissioned by
CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring
and Audit (EM&A) programme described in the approved EM&A Manual and
required under Clause 4 of the Variation
of Future Environmental Permit (No. EP-01/122/2003/A) issued to Leighton-China
State-Van Oord Joint Venture in December 2007 for the CRIII Project. An Independent Environmental Checker (IEC) has
been employed to audit the EM&A programme.
The CRIII Project Organisation is shown in Annex A.
The works undertaken in the project area
requiring environmental monitoring and audit as identified in the EIA Report
(not including
·
Dredging in FRAW;
·
Rockfilling for the seawall mound in FRAW and
placement seawall blocks;
·
Reclamation filling in FRAW;
·
Placement of seawall blocks in FRAE
·
Rockfilling in FRAE;
·
Pile cap construction for Public Pier East (Pier
No.10);
·
Preservation works at Queen’s Pier;
·
Excavation of temporary drainage channel at the
former Star Ferry;
·
Remedial and outstanding works at and around Piers
7 & 8 and the CTB;
·
Remedial and outstanding works at Public Pier West;
·
Remedial and outstanding works at MYS Footbridge;
·
General filing works above +2.5 mPD in IRAE;
·
Construction of storm and foul drainage in
hinterlands for Road P2, Road D7, Road D8 and Road D9 and adjacent to the GPO;
·
Reinstatement of existing Culvert J;
·
Temporary works and excavation for Road P2
Underpass;
·
Pipe jointing associated with the stabilisation of
the U-Trap structure;
·
Roadworks
along
·
Demolition of former pump
stations at CR-18;
·
Temporary
works, excavation and piling for Culvert F extension; and
·
Temporary
works and excavation for Culvert K extension.
2.1
Summary of Impact EM&A Requirements
The EM&A
programme requires environmental monitoring for air quality, noise, waster
quality, waste management and landscape and visual aspects as specified in the
CRIII Project EIA. The EM&A
requirements for each issue area are described in subsequent sections
including:
·
All required monitoring parameters;
·
Action and Limit Levels; and
·
Event-Action Plans.
A summary of
impact EM&A requirements is presented in Table 2-1.
Table 2.1 - Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
Duration |
|
TSP |
24-Hour TSP |
2 Locations |
Once every 6 days |
During dust generating construction works |
|
1-Hour TSP |
2 Locations |
Three times in every 6 days |
During dust generating construction works |
|
|
Noise |
Leq (30 mins), L10, L90, |
1 Location |
Continuous measurements |
Two weeks before Construction and During Construction |
|
Water Quality |
Dissolved Oxygen; Salinity; Temp; Suspended Solids; Turbidity. |
16 Locations |
3 times a week, Mid-ebb/flood tides |
During Marine Works and for 4 weeks after completion of
Marine Works |
|
Waste |
On-Site Waste Audit |
Active Work Sites |
Periodically |
During Construction |
|
On-Site Waste Inspection |
||||
|
Landscape and Visual |
Audits to ensure effective implementation of
mitigation measures |
During Construction |
||
|
General Site Conditions |
Environmental Site Inspection |
Works areas and areas affected by works |
Periodically |
During Construction |
2.2
Environmental Quality Performance Limits
Environmental Quality
Performance Limits for air quality, noise and water quality have been
established as part of the Baseline Monitoring Report and are provided in Annex
B.
Event Action
Plans for air quality, noise and water quality have been developed as part of
the Baseline Monitoring Report and are provided in Annex C.
3.1
Implementation of Environmental Measures
The Contractor
has implemented relevant mitigation measures listed in the EIA Report, EM&A
Manual and Further Environmental Permit.
3.2
Environmental Monitoring Locations
Drawings showing
the project area and locations of the monitoring stations are provided in Annex
D.
3.3
Air Quality Monitoring Results
The graphical
plot of air quality monitoring results for this reporting quarter is provided
in Annex F.
3.4
Noise Quality Monitoring Results
The graphical
plot of noise monitoring results for this reporting quarter is provided in Annex
G.
3.5
Water Quality Monitoring Results
The graphical plot
of water quality monitoring results for this reporting quarter is provided in Annex
H.
3.6
Solid and Liquid Waste Management Status
Solid and liquid
waste management was implemented according to the Waste Management Plan during
this reporting quarter.
3.7
Landscape and Visual Audit
As the works undertaken during this reporting quarter were mainly
related to reclamation, buildings and infrastructure works, the landscape and
visual impacts are considered to be minimal.
4.1
Environmental Exceedances
No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.
One noise exceedance was recorded at the City Hall
monitoring station on
Exceedances of water quality were recorded on 15 sampling days in this reporting quarter. Exceedances of the Action Limit for DO were recorded on 7 of the sampling days. Exceedances of the Action Limit for SS were recorded on 8 of the sampling days. Exceedances of the Limit Level for SS were recorded on 4 of the sampling days. All exceedances have been investigated and were not considered to have been directly related to project works as no marine works nor run-off from the site were observed during the monitoring days. The exceedances could be attributed to natural variation in ambient conditions and other external factors rather than the project works. The water quality exceedances during this reporting quarter is summarised in Table 4.1.
Table 4.1 - Summary Water Quality Exceedances From November 2007 to
January 2008
|
Date |
Tide |
Parameter |
Exceedance |
Station |
|
2nd
Nov 07 |
Mid-ebb |
DO |
|
M1A, M2A, M3_M5A, M4B and M5B |
|
Mid-flood |
SS |
|
M3_M5A |
|
|
7th Nov 07 |
Mid-ebb |
SS |
|
M3_M5A and M5B |
|
9th Nov 07 |
Mid-flood |
SS |
|
M12 |
|
12th Nov 07 |
Mid-flood |
SS |
LL |
M6 and M12 |
|
14th Nov 07 |
Mid-flood |
DO |
|
M12 |
|
16th Nov 07 |
Mid-ebb |
DO |
|
M1A, M2A, M3_M5A, M4B, M5B and M11 |
|
21st Nov 07 |
Mid-flood |
SS |
|
M6 |
|
|
Mid-ebb |
DO |
|
M1A, M2A, M4B, M5B, M6, M11 and M12 |
|
Mid-flood |
DO |
|
M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12 |
|
|
|
Mid-ebb |
SS |
LL |
M11 |
|
|
Mid-flood |
SS |
|
M6 |
|
|
Mid-ebb |
DO |
|
M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12 |
|
Mid-flood |
DO |
|
M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12 |
|
|
|
Mid-ebb |
DO |
|
M6 and M12 |
|
SS |
|
M6 |
||
|
Mid-flood |
DO |
|
M2A, M3_M5A, M4B, M5B, M6, M11 and M12 |
|
|
|
Mid-ebb |
DO |
|
M6 |
|
|
Mid-flood |
SS |
|
M6 |
|
LL |
M12 |
|||
|
|
Mid-flood |
SS |
|
M6 |
|
LL |
M12 |
A statistical
analysis (presented in Annex I) of the suspended solids
monitoring results found that the quarterly mean is significantly less than 1.3
times of the ambient mean recorded during the baseline period. This indicates that the Project construction
works did not cause adverse impacts during the reporting period with respect to
the baseline condition.
No environmental non-compliances
were reported in this quarter.
4.3
Summary of Actions Taken by the Contractor
The Contractor
has implemented the following measures to prevent air and water quality
impacts:
·
Contractor has implemented their Drainage
Management Plan to Control Site Run-off for the wet season – actions completed
and underway include: repair and improvement of existing bunds/sandbags on the
edge of the reclamation; installation of additional bunds; compaction of soil
surface and pathing where possible to prevent erosion, creation of drainage
channels and soak pits.
·
Provision a single WetSep flocculation based
water treatment plant and additional settlement tanks to remove suspended
solids from discharge waters;
·
Provision of catch pits to collect spill over from
wheel washing facilities; increased frequency of cleaning of catch-pits;
·
Water browsing of haul roads and other areas of the
site and covering of stockpiles.
No environmental enquiries were received during this reporting quarter.
4.5
Environmental Complaints and Prosecutions
No environmental complaints were received
during this reporting quarter.
4.6
Record of Environmental Complaints and Summons & Prosecutions
There was no record of environmental complaints during this reporting
quarter.
There were no notifications
of summons and prosecutions during this reporting quarter.
During the environmental site inspections conducted within this
reporting quarter, no non-compliances were noted and no prosecutions were
received during this reporting quarter.
No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.
One noise exceedance was recorded at the City Hall
monitoring station on
Exceedances of water quality were recorded on 15 sampling days in this reporting quarter. Exceedances of the Action Limit for DO were recorded on 7 of the sampling days. Exceedances of the Action Limit for SS were recorded on 8 of the sampling days. Exceedances of the Limit Level for SS were recorded on 4 of the sampling days. All exceedances have been investigated and were not considered to have been related to project works. The exceedances could be attributed to natural variation in ambient conditions and other external factors rather than the project works.
.