Central Reclamation, Phase III

Quarterly EM&A Report No. 18

(November 2007 through January 2008)

 

 


Client                     

Civil Engineering Development Department, Hong Kong
Hong Kong Island
and Islands Development Office

Project                           

Supplementary Agreement No. 3 to Agreement No. CE 15/94
Central Reclamation, Phase III

Design and Construction for the Minimum Option

Report No.

3128-REP-299-00

Copy No.

Date of Issue

14 February 2008

File Ref. L:\S-proj\CR3\CR3.NEW\3128\
            Reports\299.doc

Report Title

 

Central Reclamation, Phase III

Quarterly EM&A Report No. 18

November 2007 through January 2008

 

 

Name

 

Sign

 

Date

 

Prepared by:

Wing Wong, ACL -
Senior Environmental Consultant

 

 

 

14 February 2008

 

Reviewed by:

Susana Bezy, ACL – ET Leader

 

 

 

14 February 2008

 

Authorised by:

Jon Varndell, ACL – Project Mgr

 

 

 

14 February 2008

 

 

 

 

Distribution

 

 

Copy No

Issue to

Attention

Corr. Ref.

1

CEDD

Mr. Eric K.W. Fung

3128/M45/200/OC10078/SB/DS/KC/ec

2, 3

EPD

Director of EPD

3128/M45/200/OC10078/SB/DS/KC/ec

4

EPD (LCO)

Miss W. Y. Yiu

3128/M45/200/OC10078/SB/DS/KC/ec

5

Leighton-China State-Van Oord JV

Mr. Malcolm Plummer

3128/M45/200/OC10078/SB/DS/KC/ec

6

CRIII Sites/PRE

Mr. Douglas Miller

3128/M45/200/OC10078/SB/DS/KC/ec

7

Independent Checker (Environment)

Mr. Bill Douglas

3128/M45/200/OC10078/SB/DS/KC/ec

8

Environmental Team Leader

Ms Susana Bezy

3128/M45/200/OC10078/SB/DS/KC/ec

9

Office Copy

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


1.           Introduction. 1

1.1         Basic Project Information. 1

1.2         Project Organisation and Management Structure. 1

1.3         Works Undertaken. 2

2.           EM&A Requirements. 3

2.1         Summary of Impact EM&A Requirements. 3

2.2         Environmental Quality Performance Limits. 3

2.3         Event Action Plan. 4

3.           Environmental Status. 5

3.1         Implementation of Environmental Measures. 5

3.2         Environmental Monitoring Locations. 5

3.3         Air Quality Monitoring Results. 5

3.4         Noise Quality Monitoring Results. 5

3.5         Water Quality Monitoring Results. 5

3.6         Solid and Liquid Waste Management Status. 5

3.7         Landscape and Visual Audit 5

4.           Environmental Complaint and Non-Compliance. 7

4.1         Environmental Exceedances. 7

4.2         Non-Compliance. 8

4.3         Summary of Actions Taken by the Contractor 8

4.4         Environmental Enquiries. 8

4.5         Environmental Complaints and Prosecutions. 8

4.6         Record of Environmental Complaints and Summons & Prosecutions. 8

5.           Conclusion. 1


List of Annexes

Annex A              Project Organisation/ Contact Information

Annex B              Quality Performance Limits for Air, Noise and Water Quality

Annex C              Event and Action Plans for Air, Noise and Water Quality

Annex D              Monitoring Stations Locations

Annex E              Contractor's Works Programme

Annex F              Graphical Representation of Air Quality Monitoring Results

Annex G             Graphical Representation of Noise Quality Monitoring Results

Annex H              Graphical Representation of Water Quality Monitoring Results

Annex I               Quarterly Assessment of Construction Impacts on Suspended Solids

 

 

 

List of Tables

Table 2.1 - Summary of Impact EM&A Requirements. 3

 

 

 


 

ACL

Atkins China Limited

AL

Action Level

CEDD

Civil Engineering and Development Department

CRIII

Central Reclamation Phase III

DO

Dissolved Oxygen

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EM&A

Environmental Monitoring and Audit

EPD

Environmental Protection Department

ER

Engineer’s Representatives

ET

Environmental Team

IEC

Independent Environmental Checker

LCSD

Leisure and Cultural Services Department

LCSVO-JV

Leighton China State Van Oord Joint Venture

LL

Limit Level

PLA

People's Liberation Army Forces Hong Kong

TDD

Territory Development Department

TSP

Total Suspended Particulates

SS

Suspended Solids

WMP

Waste Management Plan

 


 


Executive Summary

The Central Reclamation Phase III (CRIII) Works, Contract No. HK 12/02, was awarded to Leighton China State Van Oord Joint Venture (LCSVO-JV) by the Civil Engineering and Development Department (CEDD). (Previously called the Territory Development Department before merger with the Civil Engineering Department on 1st July 2004.)

The works under the Contract HK 12/02 commenced on 28th February 2003.  Contract HK 16/03 for the CRIII Hinterland Drainage Improvement Works was awarded to Wang Kee Construction Co. Ltd., and works for this contract commenced on 17th December 2003.

Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual for the CRIII Project.

This is the 18th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report.  This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st November 2007 to 31st January 2008.

Environmental Monitoring and Audit Progress

Air quality, noise and water quality monitoring were conducted during this quarter.  Weekly environmental site inspections were also conducted during this reporting quarter.

Exceedance of Action and Limit Levels

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

One noise exceedance was recorded at the City Hall monitoring station in this reporting quarter.  The exceedance has been investigated and was considered to have been attributed to other external factors and unlikely to be related to project works.

Water quality exceedances were recorded on 15 sampling days in this reporting quarter.  The exceedances have been investigated and were considered to be attributed to other external factors and unlikely to be related to project works.

Complaint Log

There were no complaints received in relation to environment impact during this reporting quarter.

Notifications of Summons and Prosecutions

There were no notifications of summons or prosecutions received during this reporting quarter.

Site Inspection and Audit

Weekly environmental site inspections were carried out during this quarter.  Minor deficiencies noted during the site inspections were rectified by the Contractor upon receipt of notification.


 


1.               Introduction

1.1            Basic Project Information

The Main Works Contract HK 12/02 for CRIII commenced on 28th February 2003 and was awarded to Leighton-China State-Van Oord Joint Venture (LCSVO-JV) for the construction of the CRIII Engineering Works.  The main construction works that were identified in the EIA Report for the Project, requiring environmental monitoring and audit, have commenced.

This is the 18th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report.  This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st November 2007 to 31st January 2008.

The Contractor's works programme for the quarter is provided in Annex E.

1.2            Project Organisation and Management Structure

Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual and required under Clause 4 of the Variation of Future Environmental Permit (No. EP-01/122/2003/A) issued to Leighton-China State-Van Oord Joint Venture in December 2007 for the CRIII Project. An Independent Environmental Checker (IEC) has been employed to audit the EM&A programme. 

The CRIII Project Organisation is shown in Annex A.


1.3            Works Undertaken

The works undertaken in the project area requiring environmental monitoring and audit as identified in the EIA Report (not including Chai Wan Basin) during this reporting quarter include:

·        Dredging in FRAW;

·        Rockfilling for the seawall mound in FRAW and placement seawall blocks;

·        Reclamation filling in FRAW;

·        Placement of seawall blocks in FRAE

·        Rockfilling in FRAE;

·        Pile cap construction for Public Pier East (Pier No.10);

·        Preservation works at Queen’s Pier;

·        Excavation of temporary drainage channel at the former Star Ferry;

·        Remedial and outstanding works at and around Piers 7 & 8 and the CTB;

·        Remedial and outstanding works at Public Pier West;

·        Remedial and outstanding works at MYS Footbridge;

·        General filing works above +2.5 mPD in IRAE;

·        Construction of storm and foul drainage in hinterlands for Road P2, Road D7, Road D8 and Road D9 and adjacent to the GPO;

·        Reinstatement of existing Culvert J;

·        Temporary works and excavation for Road P2 Underpass;

·        Pipe jointing associated with the stabilisation of the U-Trap structure;

·        Roadworks along Lung Wui Road and Tim Wa Avenue (Road) D8;

·        Demolition of former pump stations at CR-18;

·        Temporary works, excavation and piling for Culvert F extension; and

·        Temporary works and excavation for Culvert K extension.

 

 


2.               EM&A Requirements

2.1            Summary of Impact EM&A Requirements

The EM&A programme requires environmental monitoring for air quality, noise, waster quality, waste management and landscape and visual aspects as specified in the CRIII Project EIA.  The EM&A requirements for each issue area are described in subsequent sections including:

·        All required monitoring parameters;

·        Action and Limit Levels; and

·        Event-Action Plans.

A summary of impact EM&A requirements is presented in Table 2-1.

Table 2.1 - Summary of Impact EM&A Requirements

Parameters

Descriptions

Locations

Frequencies

Duration

TSP

24-Hour TSP

2 Locations

Once every 6 days

During dust generating construction works

1-Hour TSP

2 Locations

Three times in every 6 days

During dust generating construction works

Noise

Leq (30 mins), L10, L90,

1 Location

Continuous measurements

Two weeks before Construction and During Construction

Water Quality

Dissolved Oxygen;

Salinity;

Temp;

Suspended Solids;

Turbidity.

16 Locations

3 times a week, Mid-ebb/flood tides

During Marine Works and for 4 weeks after completion of Marine Works

Waste

On-Site Waste Audit

Active Work Sites

Periodically

During Construction

On-Site Waste Inspection

Landscape and Visual

Audits to ensure effective implementation of mitigation measures

During Construction

General Site Conditions

Environmental Site Inspection

Works areas and areas affected by works

Periodically

During Construction

 

2.2            Environmental Quality Performance Limits

Environmental Quality Performance Limits for air quality, noise and water quality have been established as part of the Baseline Monitoring Report and are provided in Annex B.

2.3            Event Action Plan

Event Action Plans for air quality, noise and water quality have been developed as part of the Baseline Monitoring Report and are provided in Annex C.


3.               Environmental Status

3.1            Implementation of Environmental Measures

The Contractor has implemented relevant mitigation measures listed in the EIA Report, EM&A Manual and Further Environmental Permit.  

3.2            Environmental Monitoring Locations

Drawings showing the project area and locations of the monitoring stations are provided in Annex D. 

3.3            Air Quality Monitoring Results

The graphical plot of air quality monitoring results for this reporting quarter is provided in Annex F. 

3.4            Noise Quality Monitoring Results

The graphical plot of noise monitoring results for this reporting quarter is provided in Annex G. 

3.5            Water Quality Monitoring Results

The graphical plot of water quality monitoring results for this reporting quarter is provided in Annex H. 

3.6            Solid and Liquid Waste Management Status

Solid and liquid waste management was implemented according to the Waste Management Plan during this reporting quarter.

3.7            Landscape and Visual Audit

As the works undertaken during this reporting quarter were mainly related to reclamation, buildings and infrastructure works, the landscape and visual impacts are considered to be minimal.

 


 


4.               Environmental Complaint and Non-Compliance

4.1            Environmental Exceedances

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

One noise exceedance was recorded at the City Hall monitoring station on 14th January 2008.  On 14th January 2008, there were Ceremonial Opening of the Legal Year 2008 activities in front of the City Hall during the exceedances period.  The exceedances have been investigated and were considered to be attributed to other external factors and unlikely to be related to project works.

Exceedances of water quality were recorded on 15 sampling days in this reporting quarter.  Exceedances of the Action Limit for DO were recorded on 7 of the sampling days.  Exceedances of the Action Limit for SS were recorded on 8 of the sampling days. Exceedances of the Limit Level for SS were recorded on 4 of the sampling days.  All exceedances have been investigated and were not considered to have been directly related to project works as no marine works nor run-off from the site were observed during the monitoring days.  The exceedances could be attributed to natural variation in ambient conditions and other external factors rather than the project works.  The water quality exceedances during this reporting quarter is summarised in Table 4.1.

Table 4.1 - Summary Water Quality Exceedances From November 2007 to January 2008

Date

Tide

Parameter

Exceedance

Station

2nd Nov 07

Mid-ebb

DO

AL

M1A, M2A, M3_M5A, M4B and M5B

Mid-flood

SS

AL

M3_M5A

7th Nov 07

Mid-ebb

SS

AL

M3_M5A and M5B

9th Nov 07

Mid-flood

SS

AL

M12

12th Nov 07

Mid-flood

SS

LL

M6 and M12

14th Nov 07

Mid-flood

DO

AL

M12

16th Nov 07

Mid-ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B and M11

21st Nov 07

Mid-flood

SS

AL

M6

14th Dec 2007

Mid-ebb

DO

AL

M1A, M2A, M4B, M5B, M6, M11 and M12

Mid-flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

21st Dec 2007

Mid-ebb

SS

LL

M11

27th Dec 2007

Mid-flood

SS

AL

M6

31st Dec 2007

Mid-ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

2nd Jan 2008

Mid-ebb

DO

AL

M6 and M12

SS

AL

M6

Mid-flood

DO

AL

M2A, M3_M5A, M4B, M5B, M6, M11 and M12

4th Jan 2008

Mid-ebb

DO

AL

M6

23rd Jan 2008

Mid-flood

SS

AL

M6

LL

M12

30th Jan 2008

Mid-flood

SS

AL

M6

LL

M12

A statistical analysis (presented in Annex I) of the suspended solids monitoring results found that the quarterly mean is significantly less than 1.3 times of the ambient mean recorded during the baseline period.  This indicates that the Project construction works did not cause adverse impacts during the reporting period with respect to the baseline condition.

4.2            Non-Compliance

No environmental non-compliances were reported in this quarter.

4.3            Summary of Actions Taken by the Contractor

The Contractor has implemented the following measures to prevent air and water quality impacts:

·        Contractor has implemented their Drainage Management Plan to Control Site Run-off for the wet season – actions completed and underway include: repair and improvement of existing bunds/sandbags on the edge of the reclamation; installation of additional bunds; compaction of soil surface and pathing where possible to prevent erosion, creation of drainage channels and soak pits. 

·        Provision a single WetSep flocculation based water treatment plant and additional settlement tanks to remove suspended solids from discharge waters;

·        Provision of catch pits to collect spill over from wheel washing facilities; increased frequency of cleaning of catch-pits;

·        Water browsing of haul roads and other areas of the site and covering of stockpiles.

4.4            Environmental Enquiries

No environmental enquiries were received during this reporting quarter.

4.5            Environmental Complaints and Prosecutions

No environmental complaints were received during this reporting quarter.

4.6            Record of Environmental Complaints and Summons & Prosecutions

There was no record of environmental complaints during this reporting quarter.

There were no notifications of summons and prosecutions during this reporting quarter.

 


5.               Conclusion

During the environmental site inspections conducted within this reporting quarter, no non-compliances were noted and no prosecutions were received during this reporting quarter.

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

One noise exceedance was recorded at the City Hall monitoring station on 14th January 2008.  There were Ceremonial Opening of the Legal Year 2008 activities in front of the City Hall during the exceedances period on that day.  The exceedances have been investigated and were considered to be attributed to other external factors and unlikely to be related to project works.

Exceedances of water quality were recorded on 15 sampling days in this reporting quarter.  Exceedances of the Action Limit for DO were recorded on 7 of the sampling days.  Exceedances of the Action Limit for SS were recorded on 8 of the sampling days. Exceedances of the Limit Level for SS were recorded on 4 of the sampling days.  All exceedances have been investigated and were not considered to have been related to project works.  The exceedances could be attributed to natural variation in ambient conditions and other external factors rather than the project works.

.