Central Reclamation, Phase III

Quarterly EM&A Report No. 24

(May 2009 through July 2009)


1.           Introduction. 1

1.1         Basic Project Information. 1

1.2         Project Organisation and Management Struc ture.. 1

1.3         Works Undertaken. 1

2.           EM&A Requirements. 3

2.1         Summary of Impact EM&A Requirements. 3

2.2         Environmental Quality Performance Limits. 3

2.3         Event Action Plan. 4

3.           Environmental Status. 5

3.1         Implementation of Environmental Measures. 5

3.2         Environmental Monitoring Locations. 5

3.3         Air Quality Monitoring Results. 5

3.4         Noise Quality Monitoring Results. 5

3.5         Water Quality Monitoring Results. 5

3.6         Solid and Liquid Waste Management Status. 5

3.7         Landscape and Visual Audit 5

4.           Environmental Complaint and Non-Compliance.. 7

4.1         Environmental Exceedances. 7

4.2         Non-Compliance.. 9

4.3         Summary of Actions Taken by the Contractor 9

4.4         Environmental Enquiries. 9

4.5         Environmental Complaints and Prosecutions. 10

4.6         Record of Environmental Complaints and Summons & Prosecutions. 10

5.           Conclusion. 11


List of Annexes

Annex A            Project Organisation/ Contact Information

Annex B             Quality Performance Limits for Air, Noise and Water Quality

Annex C            Event and Action Plans for Air, Noise and Water Quality

Annex D            Monitoring Stations Locations

Annex E             Contractor's Works Programme

Annex F             Graphical Representation of Air Quality Monitoring Results

Annex G            Graphical Representation of Noise Quality Monitoring Results

Annex H            Graphical Representation of Water Quality Monitoring Results

Annex I              Quarterly Assessment of Construction Impacts on Suspended Solids

 

 

 

 

List of Tables

Table 2.1 - Summary of Impact EM&A Requirements. 3

Table 4.1 - Summary Water Quality Exceedances from May 2009 to July 2009  7

 

 


Abbreviations & Acronyms

ACL

Atkins China Limited

AL

Action Level

CEDD

Civil Engineering and Development Department

CRIII

Central Reclamation Phase III

DO

Dissolved Oxygen

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EM&A

Environmental Monitoring and Audit

EPD

Environmental Protection Department

ER

Engineer’s Representatives

ET

Environmental Team

IEC

Independent Environmental Checker

LCSD

Leisure and Cultural Services Department

LCSVO-JV

Leighton China State Van Oord Joint Venture

LL

Limit Level

PLA

People's Liberation Army Forces Hong Kong

TDD

Territory Development Department

TSP

Total Suspended Particulates

SS

Suspended Solids

WMP

Waste Management Plan

 

 


Executive Summary

The Central Reclamation Phase III (CRIII) Works, Contract No. HK 12/02, was awarded to Leighton China State Van Oord Joint Venture (LCSVO-JV) by the Civil Engineering and Development Department (CEDD). (Previously called the Territory Development Department before merger with the Civil Engineering Department on 1st July 2004.)

The works under the Contract HK 12/02 commenced on 28th February 2003.  Contract HK 16/03 for the CRIII Hinterland Drainage Improvement Works was awarded to Wang Kee Construction Co. Ltd., and works for this contract commenced on 17th December 2003.

Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual for the CRIII Project.

This is the 24th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report.  This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st May 2009 to 31st July 2009.

Environmental Monitoring and Audit Progress

Air quality, noise and water quality monitoring were conducted during this quarter.  Weekly environmental site inspections were also conducted during this reporting quarter.

Exceedance of Action and Limit Levels

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

No exceedance in noise level was recorded at the City Hall monitoring station during this reporting quarter.

Water quality exceedances were recorded on 34 sampling days in this reporting quarter.  All exceedances have been investigated.   All exceedances of Action/Limit Level for DO were considered to have not been related to the Project works. All exceedances of Action/Limit Level for SS were considered to have not been related to the Project works.

Complaint Log

There were no complaints received in relation to environment impact during this reporting quarter.

Notifications of Summons and Prosecutions

There were no notifications of summons or prosecutions received during this reporting quarter.

 

Environmental Observations

During the 12th May 2009 environmental site inspection, EPD communicated with the ET and IEC that a report of muddy water near the works area of FRAE was received on 28th April 2009. The report was relayed to the Contractor on 28th April 2009.

After investigation by the Contractor, it was reported that the muddy water was due to a very high tide on the day (+2.4 mPD) which was higher than the concrete blocks, resulting in the detachment of some existing silt curtains and subsequent seepage of muddy water. An additional new curtain to enclose the seepage was being installed at the time of the observation, however the new curtain was not long enough to enclose the area. Further to this, an additional section of silt curtain was added on the same day (28th April 09), providing appropriate enclosure of seepage. The area was monitored closely by the Contractor with no further issues noted

Site Inspection and Audit

Weekly environmental site inspections were carried out during this quarter.  Minor deficiencies noted during the site inspections were rectified by the Contractor upon receipt of notification. The observations and findings are outlined below:

7th May 2009

The access roads in IRAE and FRAW were observed dry with dust. The Contractor arranged for site staff to water the access roads appropriately.

Muddy water was observed near the mouth of culvert F. The source was identified as the piling activity in the works area of FRAW. Sediment was released from the seabed due to the piling works which could not be trapped by the silt curtain. The piling activity was stopped by the Site Supervisor immediately after such observation. The Contractor suspended the related works until the issue was resolved.

12th May 2009

During the 12th May 2009 environmental site inspection, EPD communicated with the ET and IEC that a report of muddy water near the works area of FRAE was received on 28th April 2009. The report was relayed to the Contractor on 28th April 2009.

After investigation by the Contractor, it was reported that the muddy water was due to a very high tide on the day (+2.4 mPD) which was higher than the concrete blocks, resulting in the detachment of some existing silt curtains and subsequent seepage of muddy water. An additional new curtain to enclose the seepage was being installed at the time of the observation, however the new curtain was not long enough to enclose the area. Further to this, an additional section of silt curtain was added on the same day (28th April 09), providing appropriate enclosure of seepage. The area was monitored closely by the Contractor with no further issues noted.

21st May 2009

N.A.

27th May 2009

N.A.

 

4th June 2009

The refuse skip was observed full (with flies in the vicinity) at the FRAE works area. The Contractor was reminded to ensure the refuse skip is cleared regularly and to ensure the surrounding area is clean.

A container of unidentifiable chemicals was placed on the ground without a drip tray near the refuse skip at the FRAE works area. The Contractor was reminded to store the container of unidentifiable chemicals in the chemical storage area appropriately.

11th June 2009

N.A.

18th June 2009

N.A.

25th June 2009

N.A.

2nd July 2009

N.A.

9th July 2009

N.A.

16th July 2009

N.A.

23rd July 2009

The silt curtains at culvert F were detached (due to recent typhoon). The Contractor was reminded to repair or replace the silt-curtain at culvert F as soon as possible and to ensure continuous maintenance.

30th July 2009

N.A.

 

 


1.                  Introduction

1.1              Basic Project Information

The Main Works Contract HK 12/02 for CRIII commenced on 28th February 2003 and was awarded to Leighton-China State-Van Oord Joint Venture (LCSVO-JV) for the construction of the CRIII Engineering Works.  The main construction works that were identified in the EIA Report for the Project, requiring environmental monitoring and audit, have commenced.

This is the 24th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report.  This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st May 2009 to 31st July 2009.

The Contractor's works programme for the quarter is provided in Annex E.

1.2              Project Organisation and Management Structure

Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual and required under Clause 4 of the Variation of Further Environmental Permit (No. EP-01/122/2003/A) issued to Leighton-China State-Van Oord Joint Venture in December 2007 for the CRIII Project.  A variation of the Further Environmental Permit for the Project (EP-01/122/2003/B) was granted on 26th May 2008.  This was then superseded by another variation of Further Environmental Permit for the Project (No. EP-01/122/2003/C) granted on 17th July 2008.  The CRIII Project Organisation is shown in Annex A.

1.3              Works Undertaken

The works undertaken in the project area requiring environmental monitoring and audit as identified in the EIA Report (not including Chai Wan Basin) during this reporting quarter include:

·         Type A filling in FRAW and FRAE above +2.5mPD;

·         Surcharging in FRAW and FRAE;

·         Rockfilling behind the seawalls in FRAE;

·         Construction of cantilever slab at caisson;

·         Piling for Culvert F;

·         Sheet piling, Excavation, Structural works and backfilling for Culvert F;

·         Structural works for Public Pier East (Pier No.10);

·         Structural works for the MTRC 40 metre EOT;

·         General filling works above +2.5 mPD in IRAE;

·         Construction of storm and foul drainage and gullies in hinterlands for Road P2, Road D7, Road D8 and Road D9 and adjacent to the GPO;

·         Roadworks along Lung Wui Road, Tim Wa Avenue (Road D8) and Road P2;

·         Excavation and structural works for Culvert K extension;

·         Precasting for Culvert K, seawall blocks and retaining wall (offsite);

·         Installation of cooling water mains for Tamar Development Project at IRAE;

·         Construction of staircase structure of Man Yiu Street Footbridge;

·         Site investigation and diaphragm walling for CRIII Protection Works.

 

 

 

 


2.                  EM&A Requirements

2.1              Summary of Impact EM&A Requirements

The EM&A programme requires environmental monitoring for air quality, noise, waster quality, waste management and landscape and visual aspects as specified in the CRIII Project EIA.  The EM&A requirements for each issue area are described in subsequent sections including:

·         All required monitoring parameters;

·         Action and Limit Levels; and

·         Event-Action Plans.

A summary of impact EM&A requirements is presented in Table 2-1.

Table 2.1 - Summary of Impact EM&A Requirements

Parameters

Descriptions

Locations

Frequencies

Duration

TSP

24-Hour TSP

2 Locations

Once every 6 days

During dust generating construction works

1-Hour TSP

2 Locations

Three times in every 6 days

During dust generating construction works

Noise

Leq (30 mins), L10, L90,

1 Location

Continuous measurements

Two weeks before Construction and During Construction

Water Quality

Dissolved Oxygen;

Salinity;

Temp;

Suspended Solids;

Turbidity.

16 Locations

3 times a week, Mid-ebb/flood tides

During Marine Works and for 4 weeks after completion of Marine Works

Waste

On-Site Waste Audit

Active Work Sites

Periodically

During Construction

On-Site Waste Inspection

Landscape and Visual

Audits to ensure effective implementation of mitigation measures

During Construction

General Site Conditions

Environmental Site Inspection

Works areas and areas affected by works

Periodically

During Construction

 

 

2.2              Environmental Quality Performance Limits

Environmental Quality Performance Limits for air quality, noise and water quality have been established as part of the Baseline Monitoring Report and are provided in Annex B.

2.3              Event Action Plan

Event Action Plans for air quality, noise and water quality have been developed as part of the Baseline Monitoring Report and are provided in Annex C.

 

 


3.                  Environmental Status

3.1              Implementation of Environmental Measures

The Contractor has implemented relevant mitigation measures listed in the EIA Report, EM&A Manual and Further Environmental Permit.  

3.2              Environmental Monitoring Locations

Drawings showing the project area and locations of the monitoring stations are provided in Annex D. 

3.3              Air Quality Monitoring Results

The graphical plot of air quality monitoring results for this reporting quarter is provided in Annex F. 

3.4              Noise Quality Monitoring Results

The graphical plot of noise monitoring results for this reporting quarter is provided in Annex G.    

3.5              Water Quality Monitoring Results

The graphical plot of water quality monitoring results for this reporting quarter is provided in Annex H. 

3.6              Solid and Liquid Waste Management Status

Solid and liquid waste management was implemented according to the Waste Management Plan during this reporting quarter.

3.7              Landscape and Visual Audit

As the works undertaken during this reporting quarter were mainly related to reclamation, buildings and infrastructure works, the landscape and visual impacts are considered to be minimal.

 


4.                  Environmental Complaint and Non-Compliance

4.1              Environmental Exceedances

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

No exceedance in noise level was recorded at City Hall monitoring stations during this reporting quarter.

 

Water quality exceedances were recorded on 34 sampling days in this reporting quarter.  All exceedances have been investigated. All exceedances of Action/Limit Level for DO were considered to have not been related to the Project works. All exceedances of Action/Limit Level for SS were considered to have not been related to the Project works.

The water quality exceedances during this reporting quarter are summarised in Table 4.1.

 Table 4.1 - Summary Water Quality Exceedances from May 2009 to July 2009

 

 

Date

Tide

Parameter

Exceedance

Station

Water Quality Monitoring in Accordance with EM&A Manual

6th May 2009

Mid-Ebb

SS

LL

M10

Mid-Flood

SS

AL

M6, M8, M10 and M11

LL

M12

11th May 2009

Mid-Ebb

SS

AL

M1A and M11

Mid-Flood

SS

AL

M6

13th May 2009

Mid-Flood

DO

AL

M6

15th May 2009

Mid-Flood

DO

AL

M2A, M3_M5A and M4B

18th May 2009

Mid-Ebb

DO

AL

M2A, M3_M5A, M4B, M5B and M11

Mid-Flood

DO

AL

M1A and M11

20th May 2009

Mid-Ebb

DO

AL

M2A and M4B

Mid-Flood

DO

AL

M2A and M4B

22nd May 2009

Mid-Flood

DO

AL

M3_M5A, M4B, M5B, M6 and M12

SS

AL

M5B

25th May 2009

Mid-Ebb

DO

AL

M2A, M4B and M5B

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

27th May 2009

Mid-Ebb

DO

AL

M1A and M6

Mid-Flood

DO

AL

M2A, M6 and M12

1st June 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6 and M11

3rd June 2009

Mid-Flood

DO

AL

M5B and M6

10th June 2009

Mid-Flood

DO

AL

M2A, M3_M5A, M4B, M5B and M6

12th June 2009

Mid-Ebb

DO

AL

M1A, M6, M10(S/M) and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M8(S/M), M10(S/M), M11 and M12

15th June 2009

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B and M11

SS

AL

M6

LL

M12

17th June 2009

Mid-Flood

DO

AL

M1A, M2A and M4B

SS

LL

M12

19th June 2009

Mid-Ebb

DO

AL

M8(B) and M10(B)

Mid-Flood

DO

AL

M1A, M2A, M4B, M6, M8(B) and M10(B)

22nd June 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

24th June 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M8(S/M), M10(S/M), M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M8(S/M), M10(S/M), M11 and M12

LL

M6

26th June 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M8(S/M), M11 and M12

LL

M6

30th June 2009

Mid-Flood

DO

AL

M2A, M3_M5A, M4B, M5B, M6, M12

2nd July 2009

Mid-Ebb

DO

AL

M8(B) and M10(B)

4th July 2009

Mid-Flood

DO

AL

M2A, M4B, M6 and M12

6th July 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M8(B), M10(B), M10(S/M), M11 and M12

Mid-Flood

DO

AL

M1A, M5B, M6, M8(B), M10(B), M10(S/M) and  M12

8th July 2009

Mid-Flood

DO

AL

 M1A, M3_M5A, M5B, M6, M11 and M12

10th July 2009

Mid-Flood

DO

AL

M2A and M12

13th July 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

15th July 2009

Mid-Flood

DO

AL

M2A, M3_M5A, M4B and M5B

17th July 2009

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

20th July 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

22nd July 2009

Mid-Ebb

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

Mid-Flood

DO

AL

M1A, M2A, M4B and M11

24th July 2009

Mid-Ebb

DO

AL

M12

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

27th July 2009

Mid-Flood

DO

AL

M1A, M2A, M3_M5A, M4B, M5B, M6, M11 and M12

29th July 2009

Mid-Ebb

DO

AL

M10(B)

Mid-Flood

DO

AL

M2A and M4B

31st July 2009

Mid-Ebb

DO

AL

M8(B)

Mid-Flood

DO

AL

M6, M8(B) and M10(B)

A statistical analysis (presented in Annex I) of the suspended solids monitoring results found that the quarterly mean is significantly less than 1.3 times of the ambient mean recorded during the baseline period.  This indicates that the Project construction works did not cause adverse impacts during the reporting period with respect to the baseline condition.

4.2              Non-Compliance

No non-compliance with regard to site environmental audit was recorded during the reporting period.

4.3              Summary of Actions Taken by the Contractor

The Contractor has implemented the following measures to prevent air and water quality impacts:

·         Contractor has implemented their Drainage Management Plan to Control Site Run-off for the wet season – actions completed and underway include: repair and improvement of existing bunds/sandbags on the edge of the reclamation; installation of additional bunds; compaction of soil surface and paths where possible to prevent erosion, creation of drainage channels and soak pits; 

·         Provision of additional settlement tanks to remove suspended solids from discharge waters;

·         Provision of catch pits to collect spill over from wheel washing facilities and increased frequency of cleaning of catch-pits; and

·         Water browsing of haul roads and other areas of the site and covering of stockpiles.

4.4              Environmental Enquiries

No environmental enquiries were received during this reporting quarter.

4.5              Environmental Complaints and Prosecutions

No environmental complaints were received during this reporting quarter.

4.6              Environmental Observations

During the 12th May 2009 environmental site inspection, EPD communicated with the ET and IEC that a report of muddy water near the works area of FRAE was received on 28th April 2009. The report was relayed to the Contractor on 28th April 2009.

After investigation by the Contractor, it was reported that the muddy water was due to a very high tide on the day (+2.4 mPD) which was higher than the concrete blocks, resulting in the detachment of some existing silt curtains and subsequent seepage of muddy water. An additional new curtain to enclose the seepage was being installed at the time of the observation, however the new curtain was not long enough to enclose the area. Further to this, an additional section of silt curtain was added on the same day (28th April 09), providing appropriate enclosure of seepage. The area was monitored closely by the Contractor with no further issues noted

4.7              Record of Environmental Complaints and Summons & Prosecutions

There was no record of environmental complaints during this reporting quarter.

There were no notifications of summons and prosecutions during this reporting quarter.

 

 

 


5.                  Conclusion

During the environmental site inspections conducted within this reporting quarter, no non-compliances were noted and no prosecutions were received during this reporting quarter.

No exceedance in TSP level was recorded at the two monitoring stations during this reporting quarter.

No exceedance in noise level was recorded at City Hall monitoring station during this report quarter.

Water quality exceedances were recorded on 34 sampling days in this reporting quarter.  All exceedances have been investigated.   All exceedances of Action/Limit Level for DO were considered to have not been related to the Project works. All exceedances of Action/Limit Level for SS were considered to have not been related to the Project works.