Central Reclamation,
Phase III
Quarterly EM&A
Report No. 27
(February 2010 through
April 2010)
1.2 Project Organisation and
Management Structure
2.1 Summary of Impact EM&A Requirements
2.2 Environmental Quality Performance Limits
3.1 Implementation of Environmental Measures
3.2 Environmental Monitoring Locations
3.3 Air Quality Monitoring Results
3.4 Noise Quality Monitoring Results
3.5 Water Quality Monitoring Results
3.6 Solid and Liquid Waste Management Status
3.7 Landscape and Visual Audit
4. Environmental
Complaint and Non-Compliance
4.3 Summary of Actions Taken by the Contractor
4.5 Environmental Complaints and Prosecutions
4.6 Record of Environmental Complaints and Summons
& Prosecutions
List of Annexes
Annex
A Project Organisation/
Contact Information
Annex
B Quality Performance
Limits for Air, Noise and Water Quality
Annex
C Event and Action Plans
for Air, Noise and Water Quality
Annex
D Monitoring Stations
Locations
Annex
E Contractor's Works
Programme
Annex
F Graphical Representation
of Air Quality Monitoring Results
Annex
G Graphical Representation
of Noise Quality Monitoring Results
Annex
H Graphical Representation
of Water Quality Monitoring Results
Annex
I Additional DO Water
Monitoring Results
Annex
J Quarterly Assessment of
Construction Impacts on Suspended Solids
List of Tables
Table 2.1 - Summary of Impact EM&A Requirements
Table 4.1 - Summary Water Quality Exceedances from
February 2010 to April 2010
Abbreviations & Acronyms
|
ACL |
Atkins China Limited |
|
|
Action Level |
|
CEDD |
Civil Engineering and Development Department |
|
CRIII |
Central Reclamation Phase III |
|
DO |
Dissolved Oxygen |
|
EIA |
Environmental Impact Assessment |
|
EIAO |
Environmental Impact Assessment Ordinance |
|
EM&A |
Environmental Monitoring and Audit |
|
EPD |
Environmental Protection Department |
|
ER |
Engineer’s Representatives |
|
ET |
Environmental Team |
|
IEC |
Independent Environmental Checker |
|
LCSD |
Leisure and Cultural Services Department |
|
LCSVO-JV |
|
|
LL |
Limit Level |
|
PLA |
People's Liberation Army Forces |
|
TDD |
Territory Development Department |
|
TSP |
Total Suspended Particulates |
|
SS |
Suspended Solids |
|
WMP |
Waste Management Plan |
Executive Summary
The Central Reclamation Phase III (CRIII) Works,
Contract No. HK 12/02, was awarded to Leighton China State Van Oord Joint
Venture (LCSVO-JV) by the Civil Engineering and Development Department (CEDD).
(Previously called the Territory Development Department before merger with the
Civil Engineering Department on
The works under the Contract HK 12/02 commenced on 28th February 2003. Contract HK 16/03 for the CRIII Hinterland Drainage Improvement Works was awarded to Wang Kee Construction Co. Ltd., and works for this contract commenced on 17th December 2003.
Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual for the CRIII Project.
This is the 27th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st February 2010 to 30th April 2010.
Environmental Monitoring and Audit Progress
Air quality,
noise and water quality monitoring were conducted during this quarter. Weekly environmental site inspections were
also conducted during this reporting quarter.
Additional water
quality monitoring was conducted, since 14th December, for the “the
water quality of embayment area between the eastern seawall and the Hong Kong
Convention and Exhibition Centre (HKCEC) upon completion of eastern seawall”, in
accordance with the Environmental Permit No. EP-01/122/2003/D Condition
3.9.
The water quality
monitoring conducted by the ET was
changed, as approved by EPD, since 11th January 2010, from 8
stations to 3 stations.
Exceedance of Action and Limit Levels
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
48 exceedance in noise level was recorded at the City Hall monitoring
station on 5th, 6th, 15th
and 28th February 2010; 6th, 8th, 16th,
17th, 18th, 21st and 28th March 2010;
4th, 10th, 12th, 14th,
15th, 16th, 19th, 20th, 21st,
22nd, 23rd, 24th, 26th, 27th
and 29th April 2010. On 15th February 2010, fireworks
display was carried out at night. As such, the noise exceedances are considered
to be attributed by external factors and unlikely to be related to project
works. On 21st, 28th March and 4th April 2010,
no major activities from the CRIII sites were carried out. On 5th, 6th
and 28th February 2010; 6th, 8th, 16th,
17th and 18th March 2010; 10th,
12th, 14th, 15th, 16th, 19th,
20th, 21st, 22nd, 23rd, 24th,
26th, 27th and 29th April 2010, the noise
exceedances were considered to be attributed by the extension work on Hong Kong
Planning and Infrastructure Exhibition Gallery rather than the project works. As
such, the noise exceedances are considered to be attributed by external factors
and unlikely to be related to project works.
Water quality exceedances were recorded on 10 sampling days in this
reporting quarter. All exceedances have been investigated. All exceedances of
Action/Limit Level for DO were considered to have not been related to the
Project works. All exceedances of Action/Limit Level for SS were considered to
have not been related to the Project works.
Complaint Log
There were no
complaints received in relation to environment impact during this reporting
quarter.
Notifications
of Summons and Prosecutions
There were no
notifications of summons or prosecutions received during this reporting
quarter.
Site Inspection and Audit
Weekly environmental site inspections were carried out during this
quarter. Minor deficiencies noted during
the site inspections were rectified by the Contractor upon receipt of
notification. The observations and findings are outlined below:
4th February 2010
N.A.
11th February 2010
N.A.
18th February 2010
N.A.
25th February 2010
N.A.
4th March 2010
N.A.
11th March 2010
The Contractor is reminded
to pay attention on dust suppression due to drastic changes of weather.
18th March 2010
Part of access roads was observed dry in the site area. The Contractor
is reminded to pay attention on dust suppression
due to drastic changes of weather.
25th March 2010
N.A.
1st April 2010
Tarpaulin tied on poles for preventing dust blowing from barging point
was found loosen. The Contractor was reminded to tighten the tarpaulin on poles
at barging point.
The fuel drums were placed without drip tray at FRAW works area. The Contractor
was reminded to provide drip try for fuel drums at FRAW works area.
8th April 2010
The Contractor was reminded
to inform truck drivers to switch off engines while idling.
15th April 2010
N.A.
22nd April 2010
N.A.
29th April 2010
N.A.
The Main Works Contract HK 12/02 for CRIII commenced on
This is the 27th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from 1st
February 2010 to 30th April 2010.
The
Contractor's works programme for the quarter is provided in Annex
E.
Atkins China Limited (ACL) has been commissioned by CEDD as the
Environmental Team (ET) to undertake the Environmental Monitoring and Audit
(EM&A) programme described in the approved EM&A Manual and required
under Clause 4 of the Variation of Further Environmental Permit (No.
EP-01/122/2003/A) issued to Leighton-China State-Van Oord Joint Venture in December
2007 for the CRIII Project. A variation
of the Further Environmental Permit for the Project (EP-01/122/2003/B) and
(EP-01/122/2003/C) were granted on
The works undertaken in the project area
requiring environmental monitoring and audit as identified in the EIA Report
(not including
·
Type A filling in FRAW and FRAE above +2.5mPD
·
Surcharging in FRAW and FRAE
·
Construction of cantilever slab at caisson
·
Pile cap construction at Culvert F
·
Sheet piling, excavation, structural works and
backfilling for Culvert F
·
General filling works above +2.5 mPD in IRAE
·
Construction of storm and foul drainage and gullies
in hinterlands for Road P2, Road D7, Road D8 and Road D9 and adjacent to the
GPO
·
Roadworks
along
·
Backfilling
to Culvert K extension
·
Precasting
for seawall blocks and retaining wall (offsite)
·
Installation
of cooling water mains for Tamar Development Project at IRAE
·
Installation
of cooling mains discharge pipes in FRAE
·
Diaphragm
walling and barrettes for CWB Works
· Excavation to formation level at CWB works.
The EM&A
programme requires environmental monitoring for air quality, noise, waster
quality, waste management and landscape and visual aspects as specified in the
CRIII Project EIA. The EM&A
requirements for each issue area are described in subsequent sections
including:
·
All required monitoring parameters;
·
Action and Limit Levels; and
·
Event-Action Plans.
A summary of
impact EM&A requirements is presented in Table 2-1.
Table 2.1
- Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
Duration |
|
TSP |
24-Hour
TSP |
2
Locations |
Once
every 6 days |
During
dust generating construction works |
|
1-Hour
TSP |
2
Locations |
Three
times in every 6 days |
During
dust generating construction works |
|
|
Noise |
Leq
(30 mins), L10, L90, |
1
Location |
Continuous
measurements |
Two
weeks before Construction and During Construction |
|
Water
Quality |
Dissolved
Oxygen; Salinity; Temp; Suspended
Solids; Turbidity. |
Since
11th January 2010 3
Locations (1) |
3
times a week, Mid-ebb/flood tides |
During
Marine Works and for 4 weeks after completion of Marine Works |
|
Waste |
On-Site
Waste Audit |
Active
Work Sites |
Periodically |
During
Construction |
|
On-Site
Waste Inspection |
||||
|
Landscape
and Visual |
Audits
to ensure effective implementation of mitigation measures |
During
Construction |
||
|
General
Site Conditions |
Environmental
Site Inspection |
Works
areas and areas affected by works |
Periodically |
During
Construction |
Note
(1) Seawater Intake M01A, M04B and land
based Monitoring Station “Culvert F” was monitored since 11th
January 2010
Environmental
Quality Performance Limits for air quality, noise and water quality have been
established as part of the Baseline Monitoring Report and are provided in Annex
B.
Event Action
Plans for air quality, noise and water quality have been developed as part of
the Baseline Monitoring Report and are provided in Annex C.
The Contractor
has implemented relevant mitigation measures listed in the EIA Report, EM&A
Manual and Further Environmental Permit.
Drawings showing
the project area and locations of the monitoring stations are provided in Annex
D.
The graphical
plot of air quality monitoring results for this reporting quarter is provided
in Annex F.
The graphical
plot of noise monitoring results for this reporting quarter is provided in Annex
G.
The graphical plot of water
quality monitoring results for this reporting quarter is provided in Annex
H.
The additional
water quality monitoring results, since 14th December, for the “the
water quality of embayment area between the eastern seawall and the Hong Kong
Convention and Exhibition Centre (HKCEC) upon completion of eastern seawall”, in
accordance with the Environmental Permit No. EP-01/122/2003/D Condition 3.9,
are presented in Annex I.
Solid and liquid
waste management was implemented according to the Waste Management Plan during
this reporting quarter.
As the works undertaken during this reporting quarter were mainly
related to reclamation, buildings and infrastructure works, the landscape and
visual impacts are considered to be minimal.
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
48 exceedance in noise level was recorded at the City Hall monitoring
station on 5th, 6th, 15th
and 28th February 2010; 6th, 8th, 16th,
17th, 18th, 21st and 28th March 2010;
4th, 10th, 12th, 14th,
15th, 16th, 19th, 20th, 21st,
22nd, 23rd, 24th, 26th, 27th
and 29th April 2010. On 15th February 2010, fireworks
display was carried out at night. As such, the noise exceedances are considered
to be attributed by external factors and unlikely to be related to project
works. On 21st, 28th March and 4th April 2010,
no major activities from the CRIII sites were carried out. On 5th, 6th
and 28th February 2010; 6th, 8th, 16th,
17th and 18th March 2010; 10th,
12th, 14th, 15th, 16th, 19th,
20th, 21st, 22nd, 23rd, 24th,
26th, 27th and 29th April 2010, the noise exceedances
were considered to be attributed by the extension work on Hong Kong Planning
and Infrastructure Exhibition Gallery rather than the project works. As such,
the noise exceedances are considered to be attributed by external factors and
unlikely to be related to project works.
Water quality exceedances were recorded on 10 sampling days in this reporting quarter. All exceedances have been investigated. All exceedances of Action/Limit Level for DO were considered to have not been related to the Project works. All exceedances of Action/Limit Level for SS were considered to have not been related to the Project works.
Table 4.1 - Summary
Water Quality Exceedances from February 2010 to April 2010
|
Date |
Tide |
Parameter |
Exceedance |
Station |
|
Water
Quality Monitoring in Accordance with EM&A Manual |
||||
|
1st
February 2010 |
Mid-ebb |
SS |
LL |
M1A |
|
1st
March 2010 |
Mid-flood |
SS |
|
M1A |
|
3rd
March 2010 |
Mid-ebb |
DO |
|
M1A |
|
5th
March 2010 |
Mid-ebb
& Mid flood |
DO |
|
M1A |
|
15th
March 2010 |
Mid-ebb |
DO |
|
M1A
and M4B |
|
12th
April 2010 |
Mid-flood |
DO |
|
M1A
and M4B |
|
14th
April 2010 |
Mid-ebb |
SS |
LL |
M1A |
|
19th
April 2010 |
Mid-ebb |
DO |
|
M1A |
|
23rd
April 2010 |
Mid-flood |
DO |
|
M1A |
|
26th
April 2010 |
Mid-flood |
SS |
|
M1A |
A statistical
analysis (presented in Annex J) of the suspended solids
monitoring results found that the quarterly mean is significantly less than 1.3
times of the ambient mean recorded during the baseline period. This indicates that the Project construction
works did not cause adverse impacts during the reporting period with respect to
the baseline condition.
No exceedances in additional DO water monitoring
were recorded during the reporting period.
No non-compliance with regard to site environmental audit was recorded
during the reporting period.
The
Contractor has implemented the following measures to prevent air and water
quality impacts:
·
Contractor has implemented their Drainage
Management Plan to Control Site Run-off for the wet season – actions completed
and underway include: repair and improvement of existing bunds/sandbags on the
edge of the reclamation; installation of additional bunds; compaction of soil
surface and paths where possible to prevent erosion, creation of drainage
channels and soak pits;
·
Provision of additional settlement tanks to remove
suspended solids from discharge waters;
·
Provision of catch pits to collect spill over from
wheel washing facilities and increased frequency of cleaning of catch-pits; and
·
Water browsing of haul roads and other areas of the
site and covering of stockpiles.
No environmental enquiries were received during this reporting quarter.
No environmental complaints were received during this reporting quarter.
There was no record of environmental complaints during this reporting
quarter.
There were no notifications of summons and
prosecutions during this reporting quarter.
During the environmental site inspections conducted within this
reporting quarter, no non-compliances were noted and no prosecutions were
received during this reporting quarter.
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
48 exceedance in noise level was recorded at the City Hall monitoring station on 5th, 6th, 15th and 28th February 2010; 6th, 8th, 16th, 17th, 18th, 21st and 28th March 2010; 4th, 10th, 12th, 14th, 15th, 16th, 19th, 20th, 21st, 22nd, 23rd, 24th, 26th, 27th and 29th April 2010. On 15th February 2010, fireworks display was carried out at night. As such, the noise exceedances are considered to be attributed by external factors and unlikely to be related to project works. On 21st, 28th March and 4th April 2010, no major activities from the CRIII sites were carried out. On 5th, 6th and 28th February 2010; 6th, 8th, 16th, 17th and 18th March 2010; 10th, 12th, 14th, 15th, 16th, 19th, 20th, 21st, 22nd, 23rd, 24th, 26th, 27th and 29th April 2010, the noise exceedances were considered to be attributed by the extension work on Hong Kong Planning and Infrastructure Exhibition Gallery rather than the project works. As such, the noise exceedances are considered to be attributed by external factors and unlikely to be related to project works.
Water quality
exceedances were recorded on 10 sampling days in this reporting quarter. All
exceedances have been investigated. All exceedances of Action/Limit Level for
DO were considered to have not been related to the Project works. All
exceedances of Action/Limit Level for SS were considered to have not been
related to the Project works.
No exceedances in additional DO water monitoring
were recorded during the reporting period.