Central Reclamation,
Phase III
Quarterly EM&A
Report No. 28
(May 2010 through July
2010)
1.2 Project Organisation and
Management Structure
2.1 Summary of Impact EM&A Requirements
2.2 Environmental Quality Performance Limits
3.1 Implementation of Environmental Measures
3.2 Environmental Monitoring Locations
3.3 Air Quality Monitoring Results
3.4 Noise Quality Monitoring Results
3.5 Water Quality Monitoring Results
3.6 Solid and Liquid Waste Management Status
3.7 Landscape and Visual Audit
4. Environmental
Complaint and Non-Compliance
4.3 Summary of Actions Taken by the Contractor
4.5 Environmental Complaints and Prosecutions
4.6 Record of Environmental Complaints and Summons
& Prosecutions
List of Annexes
Annex
A Project Organisation/
Contact Information
Annex
B Quality Performance
Limits for Air, Noise and Water Quality
Annex
C Event and Action Plans
for Air, Noise and Water Quality
Annex
D Monitoring Stations
Locations
Annex
E Contractor's Works
Programme
Annex
F Graphical Representation
of Air Quality Monitoring Results
Annex
G Graphical Representation
of Noise Quality Monitoring Results
Annex
H Graphical Representation
of Water Quality Monitoring Results
Annex
I Additional DO Water
Monitoring Results
Annex
J Quarterly Assessment of
Construction Impacts on Suspended Solids
List of Tables
Table 2.1 - Summary of Impact EM&A Requirements
Table 4.1 - Summary Water Quality Exceedances from
February 2010 to April 2010
Abbreviations & Acronyms
|
ACL |
Atkins China Limited |
|
|
Action Level |
|
CEDD |
Civil Engineering and Development Department |
|
CRIII |
Central Reclamation Phase III |
|
DO |
Dissolved Oxygen |
|
EIA |
Environmental Impact Assessment |
|
EIAO |
Environmental Impact Assessment Ordinance |
|
EM&A |
Environmental Monitoring and Audit |
|
EPD |
Environmental Protection Department |
|
ER |
Engineer’s Representatives |
|
ET |
Environmental Team |
|
IEC |
Independent Environmental Checker |
|
LCSD |
Leisure and Cultural Services Department |
|
LCSVO-JV |
|
|
LL |
Limit Level |
|
PLA |
People's Liberation Army Forces |
|
TDD |
Territory Development Department |
|
TSP |
Total Suspended Particulates |
|
SS |
Suspended Solids |
|
WMP |
Waste Management Plan |
Executive Summary
The Central Reclamation Phase III (CRIII) Works,
Contract No. HK 12/02, was awarded to Leighton China State Van Oord Joint
Venture (LCSVO-JV) by the Civil Engineering and Development Department (CEDD).
(Previously called the Territory Development Department before merger with the
Civil Engineering Department on
The works under the Contract HK 12/02 commenced on 28th February 2003. Contract HK 16/03 for the CRIII Hinterland Drainage Improvement Works was awarded to Wang Kee Construction Co. Ltd., and works for this contract commenced on 17th December 2003.
Atkins China Limited (ACL) has been commissioned by CEDD as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual for the CRIII Project.
This is the 28th quarterly EM&A Report for the works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results and audit findings of the EM&A program during the reporting period from 1st May 2010 to 31st July 2010.
Environmental Monitoring and Audit Progress
Air quality,
noise and water quality monitoring were conducted during this quarter. Weekly environmental site inspections were
also conducted during this reporting quarter.
Additional water
quality monitoring was conducted, since 14th December, for the “the
water quality of embayment area between the eastern seawall and the Hong Kong
Convention and Exhibition Centre (HKCEC) upon completion of eastern seawall”, in
accordance with the Environmental Permit No. EP-01/122/2003/D Condition
3.9.
The water quality
monitoring conducted by the ET was
changed, as approved by EPD, since 11th January 2010, from 8
stations to 3 stations.
Exceedance of Action and Limit Levels
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
10 exceedances in noise level was recorded at the City Hall monitoring
station on 12th, 13th, 22nd
and 24th May 2010; 2nd June 2010 and 17th July
2010. All the noise exceedances were considered to be attributed by the
extension work at Hong Kong Planning and Infrastructure Exhibition Gallery
rather than the project works. As such, the noise exceedances are considered to
be attributed by external factors and unlikely to be related to project works.
Water quality exceedances were recorded on 18 sampling days in this
reporting quarter. All exceedances have been investigated. All exceedances of
Action/Limit Level for DO were considered to have not been related to the
Project works. The exceedance of Action
Level for SS was considered to have not been related to the Project works.
Complaint Log
There were no
complaints received in relation to environment impact during this reporting
quarter.
Notifications
of Summons and Prosecutions
There were no
notifications of summons or prosecutions received during this reporting
quarter.
Site Inspection and Audit
Weekly environmental site inspections were carried out during this
quarter. Minor deficiencies noted during
the site inspections were rectified by the Contractor upon receipt of
notification. The observations and findings are outlined below:
6th May 2010
Tarpaulin
was not properly covering the cement bags.
The Contactor had placed the tarpaulin properly immediately.
13th May 2010
N.A.
20th May 2010
N.A.
27th May 2010
N.A.
3rd June 2010
N.A
10th June 2010
The
plug for one of the drip trays at IRAE was missing.
The
Contractor was reminded to provide clear labelling for waste sorting at Culvert
F.
17th June 2010
The
drip tray with missing plug IRAE was removed.
No
rubbish was found at Culvert F.
24th June 2010
N.A
30th June 2010
The
drums of chemical were found without drip tray near the sub-contractor office
at FRAW area. The contractor was reminded to provide the drip tray for
chemicals/fuel temporary storage.
The stagnant water was found at the works area under the Man Yiu Street
Footbridge. The contractor was reminded to remove the stagnant water properly
and spay the larvicide regularly to prevent the mosquito breeding.
8th July 2010
According
to contractor’s record, the larvicide spays regularly to prevent the mosquito
breeding.
15th July 2010
N.A
22nd July 2010
N.A
29th July 2010
N.A
The Main Works Contract HK 12/02 for CRIII commenced on
This is the 28th quarterly EM&A Report for the
works specified in Section 1.3 of the CRIII EIA Report. This report summarises the monitoring results
and audit findings of the EM&A program during the reporting period from 1st
May 2010 to 31st July 2010.
The
Contractor's works programme for the quarter is provided in Annex
E.
Atkins China Limited (ACL) has been commissioned by CEDD as the
Environmental Team (ET) to undertake the Environmental Monitoring and Audit
(EM&A) programme described in the approved EM&A Manual and required
under Clause 4 of the Variation of Further Environmental Permit (No.
EP-01/122/2003/A) issued to Leighton-China State-Van Oord Joint Venture in December
2007 for the CRIII Project. A variation
of the Further Environmental Permit for the Project (EP-01/122/2003/B) and
(EP-01/122/2003/C) were granted on
The works undertaken in the project area
requiring environmental monitoring and audit as identified in the EIA Report
(not including
·
Type A filling in FRAW and FRAE above +2.5mPD
·
General filling works above +2.5mPD in IRAE
·
Surcharging in FRAW and FRAE
·
Construction of cantilever slab at caisson
·
Pile cap and base slab construction at Culvert F
·
Construction of storm and foul drainage and gullies
in hinterlands for Road P2, Road D7, and Road D9
·
Construction of watermains at Road D7
·
Road
P2 Underpass ramp structures
·
Precasting
for retaining wall (offsite)
·
Installation
of cooling water mains for Tamar Development Project
·
Installation
of cooling mains discharge pipes in FRAE
·
Diaphragm
wall and barrettes for CWB Works
·
Excavation
to formation level at CWB works
·
Construction
of CWB structure
· Disposal of material off-site to Government fill banks
The EM&A
programme requires environmental monitoring for air quality, noise, waster
quality, waste management and landscape and visual aspects as specified in the
CRIII Project EIA. The EM&A
requirements for each issue area are described in subsequent sections
including:
·
All required monitoring parameters;
·
Action and Limit Levels; and
·
Event-Action Plans.
A summary of
impact EM&A requirements is presented in Table 2-1.
Table 2.1 - Summary of Impact EM&A Requirements
|
Parameters |
Descriptions |
Locations |
Frequencies |
Duration |
|
TSP |
24-Hour
TSP |
2
Locations |
Once
every 6 days |
During
dust generating construction works |
|
1-Hour
TSP |
2
Locations |
Three
times in every 6 days |
During
dust generating construction works |
|
|
Noise |
Leq
(30 mins), Leq (15 mins), L10, L90, |
1
Location |
Continuous
measurements |
Two
weeks before Construction and During Construction |
|
Water
Quality |
Dissolved
Oxygen; Salinity; Temp; Suspended
Solids; Turbidity. |
Since
11th January 2010 3
Locations (1) |
3
times a week, Mid-ebb/flood tides |
During
Marine Works and for 4 weeks after completion of Marine Works |
|
Waste |
On-Site
Waste Audit |
Active
Work Sites |
Periodically |
During
Construction |
|
On-Site
Waste Inspection |
||||
|
Landscape
and Visual |
Audits
to ensure effective implementation of mitigation measures |
During
Construction |
||
|
General
Site Conditions |
Environmental
Site Inspection |
Works
areas and areas affected by works |
Periodically |
During
Construction |
Note
(1) Seawater Intake M01A, M04B and land
based Monitoring Station “Culvert F” was monitored since 11th
January 2010
Environmental
Quality Performance Limits for air quality, noise and water quality have been
established as part of the Baseline Monitoring Report and are provided in Annex
B.
Event Action
Plans for air quality, noise and water quality have been developed as part of
the Baseline Monitoring Report and are provided in Annex C.
The Contractor
has implemented relevant mitigation measures listed in the EIA Report, EM&A
Manual and Further Environmental Permit.
Drawings showing
the project area and locations of the monitoring stations are provided in Annex
D.
The graphical
plot of air quality monitoring results for this reporting quarter is provided
in Annex F.
The graphical
plot of noise monitoring results for this reporting quarter is provided in Annex
G.
The graphical plot of water
quality monitoring results for this reporting quarter is provided in Annex
H.
The additional
water quality monitoring results, since 14th December 2009, for the
“the water quality of embayment area between the eastern seawall and the Hong
Kong Convention and Exhibition Centre (HKCEC) upon completion of eastern
seawall”, in accordance with the Environmental Permit No. EP-01/122/2003/D
Condition 3.9, are presented in Annex I.
Solid and liquid
waste management was implemented according to the Waste Management Plan during
this reporting quarter.
As the works undertaken during this reporting quarter were mainly
related to reclamation, buildings and infrastructure works, the landscape and
visual impacts are considered to be minimal.
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
10 exceedance in noise level was recorded at the City Hall monitoring
station on 12th, 13th, 22nd
and 24th May 2010; 2nd June 2010 and 17th July
2010. All the noise exceedances were considered to be attributed by the
extension work at Hong Kong Planning and Infrastructure Exhibition Gallery
rather than the project works. As such, the noise exceedances are considered to
be attributed by external factors and unlikely to be related to project works.
Water quality exceedances were recorded on 18 sampling days in this reporting quarter. All exceedances have been investigated. All exceedances of Action/Limit Level for DO were considered to have not been related to the Project works. The exceedance of Action Level for SS was considered to have not been related to the Project works.
Table 4.1 - Summary
Water Quality Exceedances from May 2010 to July 2010
|
Date |
Tide |
Parameter |
Exceedance |
Station |
|
Water Quality Monitoring in Accordance with EM&A Manual |
||||
|
28th
May 2010 |
Mid-flood |
DO |
|
M4B |
|
7th June
2010 |
Mid-ebb |
DO |
|
M1A |
|
Mid-flood |
DO |
|
M1A and M4B |
|
|
11th June
2010 |
Mid-ebb |
DO |
|
M4B |
|
Mid-flood |
DO |
|
M4B |
|
|
15th June
2010 |
Mid-flood |
DO |
|
M4B |
|
21st June
2010 |
Mid-flood |
DO |
|
M4B |
|
23rd June
2010 |
Mid-flood |
DO |
|
M4B |
|
25th June
2010 |
Mid-flood |
DO |
|
M4B |
|
28th June
2010 |
Mid-ebb |
DO |
|
M1A and M4B |
|
Mid-flood |
DO |
|
M1A and M4B |
|
|
30th June
2010 |
Mid-ebb |
DO |
|
M4B |
|
Mid-flood |
DO |
|
M1A |
|
|
LL |
M4B |
|||
|
2nd July
2010 |
Mid-flood |
DO |
|
M4B |
|
7th July
2010 |
Mid-flood |
DO |
LL |
M4B |
|
14th July
2010 |
Mid-flood |
DO |
|
M1A |
|
16th July
2010 |
Mid-flood |
DO |
|
M1A |
|
21st July
2010 |
Mid-flood |
DO |
|
M4B |
|
SS |
|
M1A |
||
|
23rd July
2010 |
Mid-flood |
DO |
|
M1A and M4B |
|
26th July
2010 |
Mid-ebb |
DO |
|
M1A and M4B |
|
Mid-flood |
DO |
|
M1A and M4B |
|
|
28th July
2010 |
Mid-flood |
DO |
|
M1A and M4B |
|
30th July
2010 |
Mid-ebb |
DO |
|
M1A |
|
Mid-flood |
DO |
|
M1A and M4B |
|
A statistical
analysis (presented in Annex J) of the suspended solids
monitoring results found that the quarterly mean is significantly less than 1.3
times of the ambient mean recorded during the baseline period. This indicates that the Project construction
works did not cause adverse impacts during the reporting period with respect to
the baseline condition.
No exceedances in additional DO water monitoring
were recorded during the reporting period.
No non-compliance with regard to site environmental audit was recorded
during the reporting period.
The
Contractor has implemented the following measures to prevent air and water
quality impacts:
·
Contractor has implemented their Drainage Management
Plan to Control Site Run-off for the wet season – actions completed and
underway include: repair and improvement of existing bunds/sandbags on the edge
of the reclamation; installation of additional bunds; compaction of soil
surface and paths where possible to prevent erosion, creation of drainage
channels and soak pits;
·
Provision of additional settlement tanks to remove
suspended solids from discharge waters;
·
Provision of catch pits to collect spill over from
wheel washing facilities and increased frequency of cleaning of catch-pits; and
·
Water browsing of haul roads and other areas of the
site and covering of stockpiles.
No environmental enquiries were received during this reporting quarter.
No environmental complaints were received during this reporting quarter.
There was no record of environmental complaints during this reporting
quarter.
There were no notifications of summons and
prosecutions during this reporting quarter.
During the environmental site inspections conducted within this
reporting quarter, no non-compliances were noted and no prosecutions were
received during this reporting quarter.
No exceedance in TSP level was recorded at the two monitoring stations
during this reporting quarter.
10 exceedance in noise level was recorded at the City Hall monitoring
station on 12th, 13th, 22nd
and 24th May 2010; 2nd June 2010 and 17th July
2010. All the noise exceedances were considered to be attributed by the
extension work at Hong Kong Planning and Infrastructure Exhibition Gallery
rather than the project works. As such, the noise exceedances are considered to
be attributed by external factors and unlikely to be related to project
works.
Water quality
exceedances were recorded on 18 sampling days in this reporting quarter. All
exceedances have been investigated. All exceedances of Action/Limit Level for
DO were considered to have not been related to the Project works. The exceedance
of Action Level for SS was considered to have not been related to the Project
works.
No exceedances in additional DO water monitoring
were recorded during the reporting period.